How To Change The Mold of FFS Machine
Step 1:Preparations before mold removal
Step 2: Remove the mold
6 seconds:Loosen the screws of the fixing plate of the forming die with an open-end wrench
16 seconds-32seconds:remove the forming die fixed on the plate.
33 seconds:remove the air pipe of the forming blow-off blocks..
37 seconds:Loosely formed blow-off blocks.
58 seconds:Loosen the four fixing screws of the forming lower die, and remove the forming lower die.
1 minute 13 seconds : Loosen the wire screws and the fixing jackscrews of the heat-sealed heating tube.
1 minute 20 seconds:Loosen the fixing jackscrew of the heat-sealing heating tube, loosen the three large station fixing screws, and take out the heating tube.
1 minute 35 seconds:The front heat seal module can be replaced by loosening the two screw.
1 minute 40 seconds:Loosen the wire screws and the fixing jackscrews of the heat-sealed heating tube.
1 minute 55 seconds: The back heat seal module can be replaced by loosening the two screw.
2 minute 22 seconds: Loosen the screws of the fixing plate of the slitter edge cutting station, Remove the front punching module
2 minute 45 seconds: remove the air pipe
2 minute 49 seconds: loosen the two diagonal fixing screws of the back punch, and remove the back punch mold.
3 minute 10 seconds:Loosen the screws of the fixing plate of the blanking station ,remove the front punch mold.
3 minute 30 seconds:Loosen and remove the upper cylinder of the blanking thrust positioning
4 minute 01 seconds:Loosen the screws of the fixing plate of the blanking station ,remove the back punch mold.
4 minute 37 seconds:Loosen the screws to remove the filling head and the filling head locating clamp
How To Change The Mold of FFS Machine
Step 1:Preparations before mold removal
Step 2: Remove the mold
6 seconds:Loosen the screws of the fixing plate of the forming die with an open-end wrench
16 seconds-32seconds:remove the forming die fixed on the plate.
33 seconds:remove the air pipe of the forming blow-off blocks..
37 seconds:Loosely formed blow-off blocks.
58 seconds:Loosen the four fixing screws of the forming lower die, and remove the forming lower die.
1 minute 13 seconds : Loosen the wire screws and the fixing jackscrews of the heat-sealed heating tube.
1 minute 20 seconds:Loosen the fixing jackscrew of the heat-sealing heating tube, loosen the three large station fixing screws, and take out the heating tube.
1 minute 35 seconds:The front heat seal module can be replaced by loosening the two screw.
1 minute 40 seconds:Loosen the wire screws and the fixing jackscrews of the heat-sealed heating tube.
1 minute 55 seconds: The back heat seal module can be replaced by loosening the two screw.
2 minute 22 seconds: Loosen the screws of the fixing plate of the slitter edge cutting station, Remove the front punching module
2 minute 45 seconds: remove the air pipe
2 minute 49 seconds: loosen the two diagonal fixing screws of the back punch, and remove the back punch mold.
3 minute 10 seconds:Loosen the screws of the fixing plate of the blanking station ,remove the front punch mold.
3 minute 30 seconds:Loosen and remove the upper cylinder of the blanking thrust positioning
4 minute 01 seconds:Loosen the screws of the fixing plate of the blanking station ,remove the back punch mold.
4 minute 37 seconds:Loosen the screws to remove the filling head and the filling head locating clamp